India: Coal power plant pipeline 2019

India: Coal power plant pipeline 2019 Last Modified: 28-Mar-2020 12:43 AM
  • 47.4 GW
    Combined capacity of coal fired power projects at various stages of approval and development that were cancelled in 2019.
  • 8.8 GW
    Combined capacity of projects that entered the 'under construction' phase.
  • 29.3 GW
    Combined capacity in pre-construction phase, down from 60.2 GW in 2018.
  • 19.3 GW
    Combined capacity of projects that are 'stranded', frozen in construction mainly due to financial problems.
  • 9.9 GW
  • 1,295 MW