5,712 MW
Coal based generation capacity commissioned across India in fiscal year 2018-19. In all 11 units in 10 plants were commissioned. During the same period, 2,179 MW of capacity was retired.

600 MW

660 MW
Unit 3 of Madhya Pradesh Power Generating Co. Ltd. (MPPGCL)'s Shri Singaji TPS at Dongalia, Madhya Pradesh commissioned in Nov 2018 taking the total installed capacity at this plant to 1,860 MW.

800 MW
Unit 12 of Telangana State Power Generation Corporation (TSGENCO)'s Kothagudem Thermal Power Station (KTPS) at Paloncha in Telangana commissioned in Jan 2019 taking the total installed capacity at this plant to 2,660 MW. BHEL was the EPC contractor and commissioned the plant in a record speed of 46 months at an estimated cost of Rs 5,700 crore.
250 MW
Unit 3 of Bhartiya Rail Bijlee Company Limited (BRBCL)'s Nabinagar Super Thermal Power Project at Sivanpur village in Nabinagar taluk in Aurangabad district, Bihar commissioned in Mar 2019 taking the total installed capacity at this plant to 750 MW. Unit 4 - 250 MW capacity is under construction. The plant was built by BHEL.
250 MW
Unit 3 of NTPC's Bongaigaon Super Thermal Power Project located at Salakati in Kokrajhar district of Assam commissioned at 00 hrs of 26 Mar 2019 taking the total installed capacity at this plant to 750 MW. The two units of 250 MW each of Bongaigaon project in Assam have already been made operational in June 2016 and March 2017.
360 MW
Unit 4 of RKM Powergen's Uchpinda Thermal Power Station located in Dabar Taluk in Janjgir - Champa district of Chhattisgarh, commissioned in Mar 2019 taking the total installed capacity at this plant to 1,440 MW.

660 MW
Unit 6 of Rajasthan Rajya Vidyut Utpadan Nigam Limited's Chhabra Thermal Power Project located near village Chowki Motipura in Baran district of Rajasthan, commissioned in Mar 2019 taking the total installed capacity at this plant to 2,320 MW.

660 MW
Unit 4 of Madhya Pradesh Power Generating Co. Ltd. (MPPGCL)'s Shri Singaji TPS at Dongalia, Madhya Pradesh commissioned in Mar 2019 taking the total installed capacity at this plant to 2,640 MW.
12 MW
Unit 1 of Dishergarh Thermal Power Plant in West Bengal commissioned in Mar 2019.
660 MW
Unit 2 of NTPC's Super Thermal Power Station located in Solapur, Maharashtra, commissioned at 0:00 hrs of 30 Mar 2019 taking the total installed capacity at this plant to 1,320 MW.
800 MW
Unit 1 of NTPC's Gadarwara Super Thermal Power Station located in Gangai village in Narsinghpur District, Madhya Pradesh, commissioned in Mar 2019.