List of airports in India with solar plants commissioned, are under construction or being planned

List of airports in India with solar plants commissioned, are under construction or being planned Last Modified: 27-May-2020 7:32 PM
  • 38
    Number of airports in India where rooftop solar and/or ground mounted solar systems have either been commissioned, are under construction or being planned.
  • 124.5 MWp
    peak installed capacity of all projects combined.
  • 77.6 MW
    Capacity commissioned to date.
  • 46.8 MWp
    Capacity under construction, tendered or being planned.
  • 750 KW
  • 5 MW
    Chandigarh Airport. 200 kWp rooftop solar PV system operational. Ground mounted, grid connected system with total capacity of 5 MWp (3 MWp in Phase I and 2 MWp in Phase II) with 3 MWp commissioned.
  • 1.5 MW
    Chennai Airport. Rooftop solar PV system operational since Aug 2016.
  • 40 MWp
  • 5 MW
    Hyderabad International Airport Ltd
  • 1.9 MW
    Jaipur Airport. 100 kWp rooftop solar and 1.8 MW ground mounted, grid connected systems operational since Feb 2018.
  • 2 MW
  • 515 kWp
    Chaudhary Charan Singh Airport, Lucknow. 2 systems 500 kWp and 15 kWp, tenders issued by AAI.
  • 7.84 MW
  • 250 KW
    Ranchi Airport
  • 1 MWp
  • 140 kWp
    Tiruchirapalli (Trichy) International Airport. Ground mounted solar PV system operational since Apr 2019.
  • 8 MW
    Hubballi Airport. Proposed ground mounted system, tender floated by AAI in Nov 2018.
  • 1 MW
    Renigunta International Airport, Tirupati. Ground mounted solar PV system operational since May 2018.
  • 4 MW
    Biju Patnaik International (BPI) Airport, Bhubaneshwar. Proposed ground mounted, grid connected system, tender floated by AAI in Jan 2019.
  • 300 kWp
    Prayagraj Airport, Uttar Pradesh. Proposed ground mounted, grid connected system, tender floated by AAI in May 2019.
  • 1 MW
    Begumpet Airport, Hyderabad. Proposed ground mounted system, tender floated by AAI in Nov 2018.
  • 5 MW
    Calicut Airport. Proposed ground mounted system, tender floated by AAI in Feb 2019.
  • 4 MW
    Tiruchirapalli (Trichy) International Airport. Proposed ground mounted system, tender floated by AAI for preparation of detailed project report (DPR) in Jan 2019. 1 MW commissioned in Apr 2019.
  • 1.2 MW
    Lal Bahadur Shastri International Airport (LBSI) in Varanasi, Uttar Pradesh. Proposed ground mounted, grid connected solar PV systems, tender issued by AAI in Apr 2018.
  • 15 MW
    Netaji Subhash Chandra Bose International Airport Kolkata. Ground mounted, grid connected system operational since Dec 2017.
  • 700 kWp
    Ahmedabad Airport. Rooftop solar system operational since Mar 2018.
  • 900 kWp
    Madurai Airport. Rooftop solar PV project with 730 kWp capacity built in phase 2 and operational since Jul 2019.
  • 1 MW
    Raja Bhoj Airport, Bhopal. Ground mounted, grid connected system operational since Mar 2019.
  • 540 kWp
    Lokpriya Gopinath Bordoloi International Airport (LGBI), Guwahati. Proposed rooftop solar system.
  • 100 kWp
    Lohegaon Airport, Pune. Proposed grid-connected flexible solar PV power plant system with AAI having floated tender Oct 2019.
  • 725 kWp
    Dibrugarh Airport, Assam. System operational since late 2019.
  • 220 kWp
    Gaya Airport, Bihar. System operational since late 2019.
  • 220 kWp
    Birsi Airport, Gondia, Maharashtra. System operational since late 2019.
  • 400 kWp
    Sri Guru Ram Das Jee International Airport, Amritsar. Project under construction.
  • 675 kWp
    Vadodara Airport. Ground mounted, grid connected system operational since Jul 2018.
  • 3.35 MW
    Kempegowda International Airport, Bengaluru. Plant spread over 8 rooftops is operational since Feb 2019.
  • 500 kWp
    Thiruvananthapuram Airport. Proposed rooftop solar PV system with AAI having floated SITC in Dec 2018.
  • 150 kWp
    Rajkot Airport. Proposed rooftop solar PV power plant system with AAI having floated tender in Aug 2017.
  • 1.5 MW
    Swami Vivekananda Airport, Raipur. Proposed grid-connected flexible solar PV power plant system with AAI having floated tender in Mar 2020.
  • 1 MW
    Devi Ahilyabai Holkar Airport, Indore. Ground mounted, grid connected system operational since Aug 2018.
  • 219 kWp
    Patna Airport. Operational.
  • 6.5 MWp
    Chennai Airport. AAI awarded contract in May 2019 and construction underway.
  • 50 kWp
    Bagdogra Airport. Rooftop solar Pv system operational since Feb 2017.
  • 100 kWp
    Jodhpur Airport. Rooftop solar PV system operational since Oct 2018.
  • 158 kWp
    Veer Savarkar International Airport, Port Blair. Rooftop solar PV system operational since Jun 2017.
  • 100 kWp
    Jaisalmer Airport.