30 MW planned installed capacity of the Kiata wind farm located 50 km north west of Horsham, Victoria, near the town of Nhill in the Hindmarsh Shire. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Renewable Energy Wind Energy Wind Farm Windlab Vestas Victoria Australia Source Windlab
21 Mar 2017 Start of construction. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Renewable Energy Wind Energy Wind Farm Windlab Vestas Victoria Australia Source Simon Corbell twitter feed
Apr 2017 Portland, Victoria firm Keppel Prince Engineering starts manufacturing turbine towers for Kiata’s wind farm project. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Victoria Australia Source Windlab | Photo credits: Simon Corbell twitter feed
06 May 2017 Horsham based MMTech completes installation of communication systems for data and mobile. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab MMTech Victoria Australia Source MMTech
23 Jul 2017 First blades start to arrive at the farm. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Victoria Australia Source Windlab
26 Jul 2017 Foundations for the turbine towers being put in place. Photo credits: Gav Reddie (Needa Screeda) Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source Gav Reddie | Photo credits: Gav Reddie (Needa Screeda)
01 Aug 2017 First tower section up at the farm! Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source Windlab
08 Aug 2017 1st of 9 turbines now in place! Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source Windlab twitter feed
16 Aug 2017 Windlab chief executive Roger Price informed the Wimmera Mail-Times that two of the nine turbines are now complete with a third and fourth on the way. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source The Wimmera Mail-Times
06 Nov 2017 Construction of the farm completed, its connected to the grid and generating power. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source Windlab
24 Jan 2018 Official opening of the farm by Victorian Minister for Energy and Climate Change Lily D'Ambrosio. Last Modified: 24-Jan-2018 2:28 PM Posted by AUS Sustainability in Energy Tags Power Sector Utility Scale Renewable Energy Wind Energy Wind Farm Windlab Vestas Keppel Prince Engineering Victoria Australia Source Windlab