15
Number of stalled or stranded hydro electric projects based on reply by Minister of Power in Parliament.
5,992 MW
potential capacity of the stalled or stranded projects. Total installed capacity hydro in the country stands at: 44,413 MW
960 MW
Polavaram, Andhra Pradesh. Developer: Polavaram Project Authority. Reasons for delay: Slow progress of works due to funds constraints.
2,000 MW
Subansiri Lower, Arunachal Pradesh/Assam. Developer: NHPC Ltd. Reasons for delay: Since 16.12.2011 works stopped due to agitation by various activists, fearing dam safety and downstream impacts of dam.
130 MW
Kashang I & II, Himachal Pradesh. Developer: HPPCL. Reasons for delay: Works on KK Link tunnel could not start due to agitation by Lippa villagers.
850 MW
Ratle, Jammu & Kashmi. Developer: GVK Ratle Hydro Electric Project Pvt Ltd. Reasons for delay: No progress since July, 2014. (Local issues/Indus Water Treaty Issues/Issues with State Govt.)
60 MW
Pallivasal, Kerala. Developer: KSEB. Reasons for delay: NA
40 MW
Tottiyar, Kerala. Developer: KSEB. Reasons for delay: The contractor has put forward a proposal for foreclosure of the Project due to their financial stringency.
400 MW
Maheshwar, Madhya Pradesh. Developer: SMHPCL. Reasons for delay: Works suspended since Nov-11 due to cash flow problem with developer.
80 MW
Koyna Left Bank, Maharashta. Developer: WRD, Maharasthra. Reasons for delay: Current expenditure on project has reached to almost original administrative approved cost level hence expenditure on the project is stopped.
206 MW
Shahpurkandi, Punja. Developer: PSPCL. Reasons for delay: Works of Dam (J&K side) stopped since 30.08.2014 due to inter-state disputes between Punjab and J&K Government.
500 MW
Teesta VI, Sikkim. Developer: Lanco Teesta Hydro Power Ltd. Reasons for delay: Almost no progress since April, 2014 (Funds Constraints).
120 MW
Rangit-IV, Sikkim Developer: Jal Power Corp. Reasons for delay: Works stopped since Oct-13 due to cash flow problem with developer.
300 MW
Panan, Sikkim Developer: Himagiri Hydro Energy Pvt Ltd. Reasons for delay: Major civil works held up for want of NGT Clearance. However, since there is no stay, developers informed that work to start shortly.
171 MW
Lata Tapovan, Uttarakhand. Developer: NTPC. Reasons for delay: Construction work stopped vide Hon’ble Supreme Court order dated 7.5.2014.
76 MW
Phata Byung, Uttarakhand. Developer: Lanco Infrastructure. Reasons for delay: Works affected due to flash flood in June, 2013. Slow pace of works & financial constraints.
99 MW
Singoli Bathwari, Uttarakhand. Developer: Larsen & Tubro. Reasons for delay: Slow pace of works.